INSULATION COORDINATION FOR TRANSMISSION LINES: COMPLETE TECHNICAL GUIDE (IEC 60071, IEC 60826, IEEE C62)
INSULATION COORDINATION FOR TRANSMISSION LINES: COMPLETE TECHNICAL GUIDE (IEC 60071, IEC 60826, IEEE C62)
1. Introduction
Insulation coordination is one of the most critical components of transmission line design. It ensures that line insulation, hardware, insulators, air clearances, towers, and surge protection systems can reliably withstand the electrical stresses imposed by:
-
lightning impulses
-
switching surges
-
temporary overvoltages (TOV)
-
power-frequency overvoltages
-
backflashovers and shielding failures
Poor insulation coordination directly leads to:
-
high line outage rates
-
unnecessary tripping
-
insulator flashover
-
equipment damage
-
reduced reliability indices (SAIDI, SAIFI)
-
unacceptable lightning performance
Modern utilities follow international standards such as:
-
IEC 60071-1 & 60071-2 (main standard for insulation coordination)
-
IEC 60826 (overhead line reliability)
-
IEEE C62 (surge protection)
-
CIGRE Technical Brochures (TB) on lightning performance
-
Utility-specific manuals (e.g., NGCP TLDS, PGES)
This article provides a comprehensive and extremely detailed methodology for conducting insulation coordination for high-voltage transmission lines ranging from 69 kV to 500 kV and beyond.
2. Objectives of Insulation Coordination
Insulation coordination aims to:
✔ Determine insulation levels
Determine the BIL (Basic Insulation Level) and SIL/SWL required for:
-
insulators
-
air clearances
-
tower geometry
-
substation interfaces
✔ Limit the probability of flashover
Maintain a design where the probability of flashover is lower than a target value defined by standards.
✔ Optimize insulation cost
Avoid overdesign (expensive, unnecessary insulation) and underdesign (prone to outages).
✔ Ensure consistency across the system
Transmission lines, substations, transformers, breakers, surge arresters must all share a coordinated insulation scheme.
3. Types of Overvoltages Considered in Insulation Coordination
3.1 Lightning Overvoltages
These are fast-front surges (1.2/50 μs) due to:
-
direct lightning strikes
-
backflashover
-
shielding failures
-
induced overvoltages
Lightning surges require insulation with sufficient BIL.
3.2 Switching Overvoltages
Slow-front surges (250/2500 μs) caused by:
-
line energization
-
line de-energization
-
reclosing
-
fault clearing
-
load rejection
At 345 kV and above, switching surges govern insulation design, not lightning.
3.3 Temporary Overvoltage (TOV)
Power-frequency sustained overvoltages from:
-
unbalanced faults
-
ferroresonance
-
ground faults
-
load rejection issues
TOV influences the withstand capabilities of long air gaps, hardware, and surge arrester duty.
3.4 Power Frequency Overvoltage
Normally occurs during:
-
phase-to-ground faults
-
load rejection
-
improper synchronizing
4. Key Insulation Parameters
4.1 BIL (Basic Insulation Level)
The withstand capability under a lightning impulse.
Typical BIL values:
-
69 kV → 325 kV BIL
-
115 kV → 550 kV BIL
-
230 kV → 1050–1100 kV BIL
-
500 kV → 1550–1800 kV BIL
4.2 CWW (Chopped Wave Withstand)
Important for switching operations where gas breakers generate chopped-wave stresses.
4.3 SIWL (Switching Impulse Withstand Level)
Governs EHV/UHV (>300 kV) lines.
Typical:
-
345 kV → ~900 kV SIWL
-
500 kV → 1050–1200 kV SIWL
4.4 CFO (Critical Flashover Voltage)
Voltage at which insulation flashes over 50% of the time.
CFO directly determines:
-
air clearance
-
tower geometry
-
insulator string length
5. Insulation Coordination Methodology (IEC 60071-2)
STEP 1 — Identify All Overvoltage Stresses
For each voltage class, determine:
-
lightning impulse stresses
-
switching impulse stresses
-
TOV stresses
-
induced overvoltages
-
arrester discharge voltages
Use:
-
EMTP simulations
-
line energization studies
-
fast-front surge modeling
STEP 2 — Determine Insulation Withstand Levels
Use withstand curves from:
-
IEC 60071 tables
-
manufacturer specs
-
CIGRE guides
Insulation types:
-
External insulation
-
air clearances
-
insulator strings
-
tower hardware
-
-
Internal insulation
-
equipment in substations
-
transformer windings
-
breaker gaps
-
Transmission lines use external insulation coordination almost exclusively.
STEP 3 — Select BIL & SIWL Values
Governed by:
-
shielding angle
-
tower height
-
lightning density (Ng)
-
ground resistivity
-
tower footing resistance
BIL must be:
-
greater than all expected lightning surges
-
compatible with surge arrester protective levels
-
coordinated with adjacent substations
STEP 4 — Determine Air Clearances
Using curves from:
-
IEC 60071-2 (air gap withstand)
-
EPRI / CIGRE
-
Utility standards
Air gap withstand depends on:
-
atmospheric correction factor (Ka)
-
altitude correction factor
-
polarity of impulse
-
gap geometry
Example clearance requirement for 230 kV:
-
phase-to-ground: 2.7–3.5 m
-
phase-to-phase: 3.5–4.5 m
STEP 5 — Shielding Against Lightning
Transmission lines must minimize:
-
backflashover
-
shielding failure flashover
a) Shielding angle
Typical:
-
230 kV: 20–30°
-
500 kV: 10–15°
b) Ground wire placement
-
1 or 2 GW wires
-
sometimes OPGW
c) Tower footing resistance
Target:
-
<10 Ω for 230–500 kV
-
lower in high lightning areas
STEP 6 — Backflashover Analysis
Backflashover occurs when:
-
lightning hits tower or shield wire
-
tower potential rises
-
insulator string flashes over
Calculate tower voltage rise:
Where:
-
I = lightning current
-
R = footing resistance
-
L = tower inductance
Flashover probability determined using:
-
CFO curves
-
EMTP models
-
CIGRE TB 63/195/411 methods
STEP 7 — Surge Arrester Coordination
Surge arresters limit overvoltage magnitude.
Insulation must satisfy:
Typical margin:
-
15% lightning
-
25% switching
At 345–500 kV lines, series compensation may require line side surge arresters.
STEP 8 — Switching Surge Evaluation
For EHV/UHV lines, switching surges dominate.
Factors:
-
line length
-
line energization sequence
-
pre-insertion resistors
-
trapped charge
-
reclosing timing
Target switching surge probability:
-
< 2% (IEC limit)
Simulated using EMTP, PSCAD, or ATP.
STEP 9 — Check Temporary Overvoltage (TOV) Performance
TOV must not exceed:
-
insulator power-frequency withstand
-
arrester thermal capability
Sources of TOV:
-
earth faults
-
resonance
-
load rejection
-
ferroresonance
TOV values can reach:
-
1.4–1.8 pu on unfaulted phases
-
2.0–2.5 pu in isolated systems
STEP 10 — Final Insulation Coordination Check
Complete check includes:
-
lightning impulse withstand
-
switching impulse withstand
-
TOV withstand
-
arrester coordination
-
clearance compliance
-
shielding performance
-
grounding adequacy
Output documentation includes:
-
insulation selection sheet
-
CFO vs surge margin table
-
shielding failure rate (SFR) calculation
-
backflashover rate (BFR)
-
EMTP simulation results
6. Lightning Performance of Transmission Lines
Utilities target:
-
< 1–3 flashes / 100 km / year on 230 kV
-
< 0.5–1 flash / 100 km / year on 500 kV
Lightning performance depends on:
-
Ng (ground flash density)
-
tower height
-
shielding angle
-
conductor height
-
ground wire position
-
footing resistance
CIGRE provides analytical models:
-
Eriksson model
-
Wagner model
-
Rusck model
-
Transmission line lightning performance model (CIGRE TB 63)
7. Insulation Coordination Example (230 kV Line)
Step-by-step:
-
Determine lightning & switching surges using EMTP
-
Select BIL = 1050 kV
-
Select SIWL = 850 kV
-
Calculate minimum air clearances
-
Model shielding with 25° angle
-
Set tower footing resistance ≤10 Ω
-
Check backflashover probability
-
Select arresters with Upl = 650–700 kV
-
Verify margins:
-
Validate performance using CIGRE SFR/BFR formulas
8. Why Transmission Line Insulation Coordination Must Be Done Professionally
Insulation coordination directly affects:
-
system reliability
-
CAPEX (insulator selection)
-
tower geometry
-
outages and SAIFI/SAIDI
-
compliance with IEC/IEEE/utility standards
Under-designed insulation → outages, failures, safety hazards
Over-designed insulation → excessive cost
9. Summary
This technical guide demonstrated that insulation coordination for transmission lines requires:
-
advanced surge modeling
-
rigorous comparison of withstand vs stress curves
-
coordinated performance of arresters, insulators, towers
-
shielding & grounding optimization
-
compliance with IEC 60071, IEEE, CIGRE
High-voltage and extra-high-voltage lines depend on precise insulation coordination to maintain safe and reliable operation under lightning and switching transient conditions.
Comments